A simple project comprises of two start-to-end parallel paths, each with three activities in series, with no interpath dependencies. The  data (in days) for each activity are shown in the diagram. Assuming that three activities in series are enough for further computations, what will be the total project duration and its standard deviation?
 

[ESE 2018 Prelims Paper I]