A can do a work in 20 days, while B can do the same work in 25 days. They started the work jointly. Few days later C alsojoined them and thus all of them completed the whole work in 10 days. All of them were paid total of ₹700. What is the share of C?

[SSC CPO 16th-March-2019-Shift-3]