62
M: +2.00/-0.50

A work can be completed by 8 boys in 48 days. If 2 boys leave after working for 24 days, then how many days will be needed to complete the remaining work?

 

[SSC CHSL 16th March 2023 Shift-4 With Answers]
A
B
C
D

EXPLANATION

...
...