For the following questions answer them individually

P alone can complete a piece of work in 10 days while Q alone can complete the same piece of work in 15 days. To complete the work in 4 days, R is hired by P and Q. How many days does R take to complete the work alone ?

 

[SSC CHSL 10th March 2023 Shift-3 With Answers]