A takes twice as much time as B and thrice as much time as C to finalise a task. Working together, they can complete the task in 8 days. The time (in days) taken by A, B and C, respectively, to complete the task is:

[SSC CGL 2nd Dec 2022 Shift-2 With Answers]
A
B
C
D

EXPLANATION

...
...
View Full Explanation