X , Y and Z can complete a work in 5 days, 15 days and 30 days, respectively. In how days can the work be completed if X is assisted by Y and Z together, on every second day?

[SSC CGL 26 July 2023 Shift 3 With Answers]
A
B
C
D

EXPLANATION

...
...
View Full Explanation