A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and Bworked together, then how much time will they take to finish the same work?
[SSC CGL 25 July 2023 Shift 3 With Answers]
A
B
C
D

EXPLANATION

...
...
View Full Explanation