75
M: +2.00/-0.50

A can finish a piece of the work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work. For how many total number of days did B work to finish the work completely?

 

[SSC CGL 11th April 2022 Shift-1 With Answers]
A
B
C
D

EXPLANATION

...
...