A, B and C can independently finish a piece of work in 18 days, ‘x’ days and 27 days respectively. A and C started working together and after 6 days B replaced both of them. If B could finish the remaining work in 16 days, what is the value of ‘x’ ?

[SBI Clerk 05 Jun 2016]