A and B can complete a piece of work in 80 and 120 days respectively. They together start the work but A left after 20 days. After another 12 days C joined B and now they complete the work in 28 more days. In how many days C can complete the work, working alone?

 

[IBPS CLERK 2015 PATTERN BASED]