For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be _______

[GATE CE 2017 Set 2]