Which of the following statements are implicit in developing the critical path network?
1) Only one time estimate is required for any activity
2) Time only is the controlling factor at this stage
3) Time and cost both are controlling factors at this stage
4) Critical events may have positive, negative, or zero float

[ESE (IES) CE 2016 P1]