A small project consists of 3 activities P, Q and R to be executed in that sequence. The relationship between time duration (in ‘Units of time -T) and corresponding total direct cost (C units) for each of the activities, for alternate mutually exclusive possible durations for each activity, are tabulated herewith:
 

For a total duration of 25 units of time, the least total direct cost for the complete project will be